Tunisia's mega projects

From a high-speed Tunis–Sfax line to a deep-water port at Enfidha and the first HVDC submarine cable to Europe — here is the timeline of the flagship projects reshaping Tunisia over the next decade.

  1. #1 · Transport

    TGV Tunis – Sousse – Sfax High-Speed Rail

    Financing

    Tunis to Sfax in under 90 minutes.

    Flagship of the 2026–2030 Development Plan: a 350 km high-speed line connecting the capital to the Sahel and the south, designed to cut the Tunis–Sfax journey from 4h to under 90 minutes and free the conventional network for freight.

    Region
    Tunis · Sousse · Sfax
    Budget
    ≈ $4.5 B
    Timeline
    2026 → 2032

    Project timeline

    1. 2026
      Feasibility update and international tender launch
    2. 2027
      Financing close (AfDB, EIB, Gulf funds)
    3. 2028
      Civil works start on the Tunis–Sousse segment
    4. 2032
      Commercial service Tunis ⇄ Sfax
  2. #2 · Ports

    Enfidha Deep-Water Port

    Financing

    Tunisia's gateway to global maritime trade.

    A new deep-water container port between Sousse and Hammamet, designed to handle the biggest post-Panamax vessels and position Tunisia as a Mediterranean trans-shipment hub alongside Tanger Med and Piraeus.

    Region
    Sousse Governorate
    Budget
    ≈ $2.8 B
    Timeline
    2026 → 2031

    Project timeline

    1. 2026
      PPP framework approved, operator pre-qualification
    2. 2027
      Final concession award
    3. 2028
      Breakwater and quay construction begins
    4. 2031
      Phase 1 operational — 1.5 M TEU capacity
  3. #3 · Transport

    Tunis–Carthage Airport Expansion

    Under construction

    From 6 to 14 million passengers per year.

    Full modernisation of Terminal 1, a new pier, expanded apron and rebuilt runway taxiways to lift capacity to ~14 M pax/year, including a dedicated low-cost concourse and direct rail link to downtown Tunis.

    Region
    Greater Tunis
    Budget
    ≈ $900 M
    Timeline
    2026 → 2030

    Project timeline

    1. 2026
      Terminal 1 modernisation works underway
    2. 2027
      New pier and apron extension delivered
    3. 2029
      Rail link to TGM/RFR commissioned
    4. 2030
      Full capacity reached
  4. #4 · Energy

    ELMED Tunisia–Italy Electricity Interconnector

    Under construction

    First HVDC link between North Africa and the EU grid.

    A 600 MW, 220 km submarine HVDC cable between Cap Bon (Tunisia) and Partanna (Sicily), co-developed by STEG and Terna with EU funding. Unlocks large-scale Tunisian solar exports to Europe and stabilises the national grid.

    Region
    Cap Bon ⇄ Sicily
    Budget
    ≈ €850 M
    Timeline
    2025 → 2028

    Project timeline

    1. 2025
      Converter station works start in Cap Bon
    2. 2026
      Subsea cable manufacturing (Prysmian)
    3. 2027
      Cable laying across the Sicilian Channel
    4. 2028
      Commissioning — first MW exported to Italy
  5. #5 · Energy

    TuNur Sahara Solar Export Project

    Planning

    Sahara sunshine powering European homes.

    A multi-gigawatt concentrated and PV solar complex in the Tunisian Sahara, paired with HVDC export to Italy and Malta. Phase 1 targets 500 MW dedicated to domestic supply plus export through ELMED.

    Region
    Kebili / Sahara
    Budget
    ≈ €1.5 B (Phase 1)
    Timeline
    2027 → 2032

    Project timeline

    1. 2026
      Authorisations and grid studies finalised
    2. 2027
      EPC tender for Phase 1 (500 MW)
    3. 2029
      Construction start in Kebili
    4. 2032
      Phase 1 online
  6. #6 · Urban

    Tunis Financial Harbour

    Planning

    North Africa's first offshore financial centre.

    A 523-hectare mixed-use waterfront district north of Tunis developed by GFH Financial Group, combining an offshore financial centre with residences, marina, hotels and a business park. Re-launch announced under the 2026–2030 Plan.

    Region
    Raoued · North Tunis
    Budget
    ≈ $3 B
    Timeline
    2026 → 2033

    Project timeline

    1. 2026
      Master plan revision and partner re-tender
    2. 2027
      Phase 1 infrastructure works
    3. 2030
      First office towers and marina delivered
    4. 2033
      Project completion
  7. #7 · Urban

    Taparura Seafront Redevelopment (Sfax)

    Under construction

    Reclaiming Sfax's coast after decades of pollution.

    Decontamination and redevelopment of 420 hectares of reclaimed land along the Sfax seafront — new beaches, marina, parks, housing and a corniche — backed by EIB and AFD under the UfM's UPFI label.

    Region
    Sfax
    Budget
    ≈ €600 M
    Timeline
    2026 → 2031

    Project timeline

    1. 2026
      Phosphogypsum site rehabilitation completed
    2. 2027
      Corniche and beach infrastructure works
    3. 2029
      First housing and hotel plots delivered
    4. 2031
      Full redevelopment online
  8. #8 · Transport

    RFR Tunis Suburban Rail Network

    Under construction

    Doubling Tunis suburban rail capacity.

    An 86 km electrified suburban rail network linking downtown Tunis to Borj Cedria, Mohamedia–Fouchana and Manouba. Line E (Tunis–Borj Cedria) opens in phases; full network targets 2028.

    Region
    Greater Tunis
    Budget
    ≈ €1.2 B
    Timeline
    2018 → 2028

    Project timeline

    1. 2024
      Line E partial opening (Tunis – Bougatfa)
    2. 2026
      Extension to Erriadh / Ezzouhour
    3. 2027
      Line D (Manouba) commissioning
    4. 2028
      Full network in service

Sources: Présidence du Gouvernement (pm.gov.tn), La Presse de Tunisie, L'Économiste Maghrébin, European Investment Bank / UPFI, GFH Financial Group, ELMED (STEG/Terna). Figures are indicative and may evolve as projects progress.